STUDI EVALUASI KETERLAMBATAN PROYEK PENINGKATAN JALAN HOTMIX LALA–KARANG JAYAe

(Study of Delay Evaluation of the Hotmix Lala – Karang Jaya Road Improvement Project)

Authors

  • Ye Fahmi Assagaf BDK Makassar
  • Sjaid S. Fais Assagaf Universitas Iqra Buru

DOI:

https://doi.org/10.47323/ujes.v3i2.200

Keywords:

Project Delay, Multiple Linear Regression Analysis, Hotmix

Abstract

The project delay occurred in the implementation of the Lala - Karang Jaya hotmix road improvement work in the 2021 fiscal year. Therefore, this study was conducted to determine what factors affect the delay in the implementation of the Lala - Karang Jaya hotmix road improvement project and find the most important factor. dominant influence it, so that it can determine the right strategy to overcome it. The data analysis methodology used is multiple linear regression analysis of the answers to the questionnaire distributed to 30 respondents from contractors, owners and consultants involved in the work of the Lala - Karang Jaya hotmix road improvement project in 2021. Based on the results of the study, the F test was obtained that simultaneously all factors have a simultaneous effect on the delay in the implementation of the Lala - Karang Jaya hotmix road improvement project with a calculated F value = 3.302 > from F table = 2.620. However, based on the partial t test, the factors that significantly influence the delay in the implementation of the Lala - Karang Jaya hotmix road improvement project are the Equipment factor (X3), with t count = 2.795 > t table = 1.7108. The most dominant factor is the Equipment factor (X3) with a coefficient of 0.291. Therefore, the strategy used to overcome this is to strive for the contractor to test the quality and quantity of the material used in accordance with technical specifications and also pay more attention to the quality of the equipment used.

References

Budiman . (1999). Keterlambatan Waktu Pelaksanaan Dan Peringkat Dari Peyebab- Peyebabnya untuk proyek yang ada di wilayah Surabaya.

Ghozali, I. (2016) Aplikasi Analisis Multivariete Dengan Program IBM SPSS 23. Edisi 8. Semarang: Badan Penerbit Universitas Diponegoro.

Kraiem, Z.K. and Dickmann, J.E., Concurrent Delays in Construction Projects, Journal of Construction Engineering and Management, ASCE,vol. 113, no. 4, 1987, pp. 591-602.

Leonda, G. (2008), Studi Keterlambatan Penyelesaian Proyek Konstruksi Pada Tahun 2007 Di Daerah Belitung, Universitas Islam Indonesia, Yogyakarta.

Muhammad Sirojul, H . A. D. I. (2021). Evaluasi Faktor-Faktor Penyebab Keterlambatan Pada Proyek Pembangunan Puskesmas Meninting (Doctoral dissertation, Universitas_Muhammadiyah_Mataram).

Purwasih, R. 2017. Pengaruh Model Project Based Learning Terhadap Hasil Belajar Siswa Pada Pembelajaran TematikKelas IVSD Negeri 1Metro Utara. Universitas Lampung

Rusito, R. (2020). Analisis Kajian Faktor-Faktor Yang Dapat Mempengaruhi Keterlambatan Proyek Jalan Di Jalan Raya Rancaekek-Cileunyi Nagreg. TECHNO-SOCIO EKONOMIKA, 12(1), 61-91.

Sianipar, H. B. (2012). Analisis Faktor-Faktor Penyebab Keterlambatan Penyelesaian Proyek Konstruksi Pengaruhnya Terhadap Biaya.

Sjafitri, H., & Zulbahri, L. (2014). Analisis Faktor-Faktor Keterlambatan Penyelesaian Proyek Infrastruktur Pembangunan Jalan. Manajemen dan Kewirausahaan, 5(3), 111-124.

Sugiyono. (2018). Metode penelitian kuantitatif, kualitatif dan R & D. Alfabeta. Bandung.

Suyatno. (2010). Analisis Faktor Penyebab Keterlambatan Peyelesaian Proyek Gedung (Aplikasi Model Regresi) untuk proyek yang ada diwilayah Surakarta.

Whidiawati. (2009). Analisis Faktor- Faktor Penyebab Keterlambatan Pelaksanaan Proyek Konstruksi untuk proyekproyek yang ada di wilayah Bali.

Downloads

Published

2022-09-01

How to Cite

Assagaf, Y. F., & Assagaf, S. S. F. . (2022). STUDI EVALUASI KETERLAMBATAN PROYEK PENINGKATAN JALAN HOTMIX LALA–KARANG JAYAe: (Study of Delay Evaluation of the Hotmix Lala – Karang Jaya Road Improvement Project). Uniqbu Journal of Exact Sciences, 3(2), 42–50. https://doi.org/10.47323/ujes.v3i2.200